Plans and Prospects | |
Offshore areas | North Sea: Borkum, Helgoland, Sylt, open North Sea |
Planned offshore windpower | 20.4 GW (41.3 GW beyond 2020) |
timing | 2020 |
Transmission System | |
TSOs | RWE Transportnetz Strom GmbH, E.ON Netz GmbH, Vattenfall Europe Transmission GmbH, EnBW Transportnetze AG |
Control zones and operators | One control zone per TSO:RWE Transportnetz Strom GmbH (west), E.ON Netz GmbH (centre), Vattenfall Europe Transmission GmbH (east), EnBW Transportnetze |
Synchronous Zone | UCTE |
Final electricity consumption (2002) [TWh] | 498,8 |
Generation capacity (2002) [GW] | 125,0 |
Peak load (2002) | |
Minimum load (2002) | |
Power Generation Portfolio [GW] | |
Nuclear | 23,40 |
Thermal (non-nuclear) | 81,09 |
Hydro | 8,48 |
Wind | 12,00 |
others | 0,00 |
Offshore Power Injection | |
Suited Substations | North Sea: Böxlund, Brunsbüttel (Vattenfall E.), Brunsbüttel (E.ON), (areas Sylt, Helgoland), |
Substation Voltage today | all 380 kV, with exception of Maade, Emden/Borssum: 220 kV |
Offshore power limit | after installation of phase shifters at substations Brunsbüttel and Diele, extensions of several existing lines inland, extension of substations (inland), provision of capacitors (inland): 476 MW offshore (2007 scenario) could be connected as scheduled but need to be curtailed at high wind/low load |
Grid issues | |
Grid code requirements | Power quality, power control not required but power curtailment, frequency control not required, voltage control (reactive power) voltage and frequency ride through. |
Balancing | Via TSO per control zone, no penalties for unbalance |
Transmission bottlenecks | generally: bottlenecks for power transmission from the rural Baltic and North Sea regions to the load centres: Rhein/Ruhr, Frankfurt, Stuttgart, München |
Necessary reinforcements | For 2020 scenario: many extensions, reinforcemens, new lines. Especially: 2 HVDC lines of a total 1050 km to the South west and South |
Timing of reinforcements | by 2007 only reinforcements or extensions of existing systems, no new lines; subsequenlty also new lines for 20 GW offshore in 2020 |
External Factors | |
Import/export/transit | Power transit from Scandinavia leads to congestion in the North already today |
other factors | |
Trans Border Capacities | |
Offshore Cable | |
Connection, first projects | |
Landing, first projects | |
Best option, long term | Assumption: Mainly initially 150 kV, later 220 kV and 400 kV gas insulated cables (GIL) Parks should be clustered in groups of several MW at an offshore substation, substations will be connected to shore via as little as possible GIL routes (2010 to 2020): environmental issue of passing the Wadden Sea (North Sea) and the Bodden Seas (Baltic) |
Connection and energy pricing | |
Connection charges for DG | |
Connection charges for offshore wind | shallow |
Priority access for renewables | yes, guaranteed by law (Erneuerbare Energien Gesetz) |
Minimum price | minimum during minimum 12 yrs at least, calculation of period and precise price according to EEG |
Webdesign and hosting Starforze
|
Webcontent © 2002 www.offshorewindenergy.org
|
Updated September 2008
|