Windfarm: NystedCountry: Denmark Location: Baltic Sea Total Capacity: 165.6 (limited to 158.4 MW) Number of Turbines: 72 Distance to Shore: 10 km Depth: 5 - 9.5 m Capital Costs: 270 million Euro Cost of Energy: Image: Status: Operational Construction Date: 2003 Manufacturer: Bonus Total Capacity: 2.3 MW Turbine-type: 82 m rotor Mean Windspeed: 9.1 m/s at 69 m hub height Annual Energy output: 595 GWh/y Windfarm Developer: Elsam/Elkraft/Energy E2 Website click here |