Windfarm: Horns Rev


Country: Denmark
Location: West Coast
Total Capacity: 160 MW
Number of Turbines: 80
Distance to Shore: 14-20 km
Depth: 6-12 m
Capital Costs: 270 million Euro
Cost of Energy:
Image:
Status:
Construction Date:
Manufacturer: Vestas
Total Capacity: 2 MW
Turbine-type: V80 - 80m diameter / 70m hubheight
Mean Windspeed: 9.7 m/s
Annual Energy output: 600 GWh
Windfarm Developer:

Location windfarm

back to map